Ballastless / Metro Track · DMRC / INDU
DMRC — Inderlok / Kirti Nagar to Mundka
19.68 km of ballastless track and 32 turnouts — the first standard-gauge ballastless turnouts laid in India.
Client
DMRC / INDU
Location
Delhi
Contract Value
₹14.81 Cr
Status
Completed
Completion
2010
19.68 km
Track laid
32
Turnouts
First in India
SG ballastless turnouts
SITE GALLERY
From the Ground

MORE IN THIS CATEGORY
More Ballastless / Metro Track Work
Ballastless / Metro TrackOngoingMMRDA Line-4 & 4A — Mumbai
Mumbai Metropolitan Region Development Authority
Ballastless trackwork on the mainline from Mulund Fire Station to Gaimukh, including Gaimukh station siding tracks and depot approach.
₹143.43 CrView Project →
Ballastless / Metro TrackMaha Metro Pune — Reach-1
Maharashtra Metro Rail Corporation
Design, supply, installation, testing and commissioning — SG ballasted track at Range Hill Depot and ballastless track on the elevated PCMC corridor.
₹61.67 CrView Project →
Ballastless / Metro TrackChennai Metro Phase-1 Extension
Chennai Metro Rail Ltd
Installation, testing and commissioning of standard-gauge ballastless track across elevated and underground sections, plus the Wimco Nagar depot.
₹61.05 CrView Project →